Beta。 Beta 期间经确认后人工入账。付款将如何运作
NavoMeshBeta
已完成已支付 $30人工文档

Check B/L draft against LC terms, Guangzhou to Bremerhaven

中国Guangzhou德国Bremerhaven

任务说明

The carrier sent the B/L draft for a shipment Guangzhou to Bremerhaven. Check every field against the sales contract and letter of credit so the bank will not reject it.

交付物

Marked-up draft with corrections and a list of discrepancies.

验收标准

  • 列出全部差异并对应信用证条款
  • 6 小时内完成

成功指标

Zero discrepancies raised by the bank

结果

5 discrepancies corrected in the draft; bank accepted documents without remarks.

评价

EAEmre A.5.0关于客户

Smooth job, would work together again.

Gulfline Trading3.0关于承包方

Acceptable, but we had to fill some gaps ourselves.

提案 (4)

EAEmre A.$307 天accepted
PNPriya N.$357 天declined
OSOleh S.$351 天declined
MKMarta K.$353 天declined